Project includes the construction of Bus Pads at existing bus stops, sidewalks, ramps, and driveways at various locations throughout the City.  The project is funded through a grant from the Federal Transit Authority (FTA).  Project went out to Bid in March 2017 and was awarded by the Commission at the April 10, 2017 meeting.

Construction Company:  RDH, LLC.
Original Contract:
Current Contract:
$261,000.00
$304,040.00
Original Contract (Days):

139 working days (May 15, 2017 – Nov. 28, 2017)


Construction Status: Construction began on May 15, 2017 and was completed on November 28, 2017.  