Hidalgo International Bridge Repaving and Joint Repair

This project consists of the milling and overlaying of 2 inches of asphalt at the Hidalgo Port of Entry.  Work is also to include repair to the bridge joint both north and south bound.  

Construction Company:     Foremost Paving Inc
Original Contract:                $ 588,663.00
Original Contract Days:      90 (calendar) Start Date May 14th 2018

Construction Status:  Construction has started.  Contractor has milled both north and south bound lanes of bridge.  Paving is 99 percent complete and striping of lanes has started.

Northbound lanes after inspection

Bridge 1

Southbound lanes

Southbound