Bond Projects: Roadway Improvements

Bicentennial (Trenton to 107)

Project being designed by Halff Associates, Inc. Sixty percent (60%) plans have been received and comments have been addressed.  Environmental Classification has been formally designated as an Environmental Assessment. Preliminary utility relocation and coordination is underway. Project letting is scheduled for May 2018.

27

27

by Alayn Arambula | 06 Feb, 2018

Leave a comment

Dove (41st to Bentsen)

Design coordination continues with Hidalgo County Irrigation District No. 1. Preliminary Environmental documentation has been submitted to TxDOT. Project is awaiting roadway functional classification from Federal Highway Administration. Construction is scheduled for Fall 2018.

27

27

by Alayn Arambula | 06 Feb, 2018

Leave a comment

Kennedy (Ware to Bentsen)

Formerly Erie Road extension project. Project being designed in house.  Right-of-Way acquisition ongoing with 1 parcel remaining to acquire (agreement in place). 

27

27

by Alayn Arambula | 06 Feb, 2018

Leave a comment

29th Street (Oxford to 107)

Project under design by Dannenbaum Engineering.  Roadway design and ROW acquisition is complete. The project has been bid out and the contract was awarded by City Commission on October 23, 2017 to 2GS, LLC in the amount of $2,515,907.70.  Construction is scheduled to begin by January 2018.

27

27

by Alayn Arambula | 06 Feb, 2018

Leave a comment

Auburn (10th to Main)

ROW acquisition is complete.  Project is under design by Melden and Hunt as part of the Northpark Village Subdivision Development Agreement. The Developer is also responsible for the construction of the roadway. 

27

27

by Alayn Arambula | 06 Feb, 2018

Leave a comment

Wisconsin (2nd to 7th)

Project constructed by private developer as part of the Embers Subdivision improvements.  City costs associated with project $401,256.15.  Construction was completed January 2016.

27

27

by Alayn Arambula | 06 Feb, 2018

Leave a comment