Bond Projects: Roadway Improvements

Bicentennial (Trenton to 107)

Project being designed by Halff Associates, Inc. Sixty percent (60%) plans have been received and comments have been addressed.  Environmental Classification has been formally designated as an Environmental Assessment. Preliminary utility relocation and coordination is underway. Project letting is scheduled for May 2018.

23

23

by Alayn Arambula | 06 Feb, 2018

Leave a comment

Dove (41st to Bentsen)

Design coordination continues with Hidalgo County Irrigation District No. 1. Preliminary Environmental documentation has been submitted to TxDOT. Project is awaiting roadway functional classification from Federal Highway Administration. Construction is scheduled for Fall 2018.

23

23

by Alayn Arambula | 06 Feb, 2018

Leave a comment

Kennedy (Ware to Bentsen)

Formerly Erie Road extension project. Project being designed in house.  Right-of-Way acquisition ongoing with 1 parcel remaining to acquire (agreement in place). 

23

23

by Alayn Arambula | 06 Feb, 2018

Leave a comment

29th Street (Oxford to 107)

Project design by Dannenbaum Engineering.  Roadway design and ROW acquisition is complete. The project was awarded by City Commission on October 23, 2017 to 2GS, LLC.  Notice to proceed with construction was issued on January 19, 2018.

Construction Company:          2GS LLC
Current  Contract:                    $ 2,758,585.32
Contract Days:                          350 Working Days

Construction Status:  As of March 31st construction is at 5%. 

29th

Auburn (10th to Main)

ROW acquisition is complete.  Project is under design by Melden and Hunt as part of the Northpark Village Subdivision Development Agreement. The Developer is also responsible for the construction of the roadway. 

23

23

by Alayn Arambula | 06 Feb, 2018

Leave a comment

Wisconsin (2nd to 7th)

Project constructed by private developer as part of the Embers Subdivision improvements.  City costs associated with project $401,256.15.  Construction was completed January 2016.

23

23

by Alayn Arambula | 06 Feb, 2018

Leave a comment

OAKLAND

On hold, pending ROW acquisition.