Lark Community Center ReRoof

This project consists of removal of the existing roofing system and replacement with new.  Existing wall surfaces at the roof level are to be resurfaced and through wall flashings upgraded to achieve a water tight assembly.

Construction Company:          SAMES, Inc.
Original Contract:                     $ 333,700.00
Contract Duration:                   90 Calendar Days

Construction Status: As of December 31, 2017, the contractor has received the bulk of the materials needed and is preparing to mobilize.

53

53

by Alayn Arambula | 06 Feb, 2018