Lark Community Center ReRoof

This project consists of removal of the existing roofing system and replacement with new.  Existing wall surfaces at the roof level are to be resurfaced and through wall flashings upgraded to achieve a water tight assembly.

Construction Company:          SAMES, Inc.
Original Contract:                     $ 333,700.00
Contract Duration:                   106 Calendar Days (11-27-17 to 3-14-18)

Construction Status: Construction began November 2017.  As of March 31, 2018, the work is now 100% complete. Additional inclement weather day extension to contract is pending. 