McAllen City Hall Re-Roof (Re-Bid) Project

This project will consist of the following a complete roof tear off and remove entire existing roofing system down to existing concrete plank deck including associated flashings and components.  Provide and install new Fully Adhered Thermoplastic Multi-Ply Roofing System including new roof insulation, tapered insulation, ½” cover-board as specified to include associated flashings, terminations, walk pads, and all associated accessories and sheet metal components for a complete installation as per the specifications.  Provide manufacture’s 20 year NDL warranty with no exclusions for leak repairs.  For up to 2” diameter hail as specified.  (Water tight 20 yr. Carlisle Golden Seal Total Roofing System Warranty-Puncture & Hail.  Refer to specifications for additional requirements.)

Construction Company: TCI Roofing and Construction, Inc.
Original Contract: $261,000.00
Original Contract (Days): 75 - Calendar Days (Aug. 16, 2017 - Sept. 30, 2017)


Construction Status:
As of December 31, 2017, the project was 137 calendar days into construction. Roofing crews have Completed 100% of the roof. 

Installation of new roof to City Hall Roof

3

3

by Alayn Arambula | 06 Feb, 2018

Leave a comment