McAllen Public Safety Building Parking Garage

This new parking structure is located behind the McAllen Public Safety Building.  The lower level will provide 158 parking spaces.  Of these, 134 parking spaces will be designated for the McAllen Police Department units while 24 parking spaces will be used for the impound lot.  The upper level of the structure will provide 136 parking spaces for staff. 

Staff will access the building via a bridge connecting the second level of the parking garage to the existing building.  The façade consists of pre-cast concrete panels.  Perforated panels will be anchored to the structure and will provide a modern look.  The perforated panels will be used to enclose the two stairwells that will be located at each end of the parking structure.  Lighting will be used to accent the stairwells and bridge in the evening hours.

Architectural Firm: Milnet Architectural Services, PLLC
Construction Company: Prodigy Construction Management, LLC
Original Contract: $3,861,320.00
Original Contract (Days): 210 - Calendar Days (Feb. 23, 2017 - Sept. 11, 2017)

Construction Status as of June, 2018:  The project is 493 calendar days into construction.  The original contract provided for 210 calendar days with an estimated completion date of September 11, 2017.  Thus far, the contractor is 283days behind schedule.  Crews are forming the shear walls.  The contractor has formed inverted T-supports and has poured 76 out of 92 inverted T-supports.   

The new estimated schedule for completion is mid-December of 2018.