McAllen Veterans War Memorial of Texas Phase II

This project consists of completing the pavers, flags and adding footings for the granite walls displays.  In addition, there will be irrigation and landscaping to enhance the features of the area. 

Construction Company: Celso Gonzalez Construction
Original Contract: $ 243,000.00
Contract Days:         90 Working Days

Construction Status: Work commenced on February 7th and is scheduled to complete on July 30th.  As of June 30, 2018, the contractor is 95% complete with pavers and irrigation.  The contactor is still pending some pavers, flag poles are being installed, minor irrigation, and grass to complete the project. The block for the art panels in the Children’s & Ceremonies areas Staff is in the process of drafting SOQs for Phase III and is to include the art work for the panels at the Children’s & Ceremonies areas.

Vet 1
Vet 2