N 6th Street at Date Palm Avenue Drainage Improvements

This project consists of upgrades to an existing storm sewer system at the intersection of N. 6th Street and Date Palm Avenue. The improvements include replacing existing storm sewer inlets and related piping. The project is funded by the Community Development Block Grant program under the FY16-17 cycle.

Construction Company:          Gonzalez Enterprises, LLC.
Original Contract:                     $ 37,985.80
Contract Days:                          15 (working)

Construction Status:  Construction began on December 19, 2017 and on December 31, 2017, the contractor completed the removal of the existing storm sewer elements and all related demolition. Crews have completed installation of the proposed inlets and laterals at the north and south ends of the intersection. The project was completed on January 12, 2018.

Inlet and curb and gutter at south end of intersection

51

51

by Alayn Arambula | 06 Feb, 2018

Leave a comment

Inlet and curb and gutter construction at north end of intersection

51

51

by Alayn Arambula | 06 Feb, 2018