Palmview Community Center ReRoof

This project consists of removal of the existing roofing system and replacement with new.  Existing wall surfaces at the roof level are to be resurfaced and through wall flashings upgraded to achieve a water tight assembly.

Construction Company:          TCI Roofing & Construction, Inc.
Original Contract:                     $ 340,000.00
Contract Duration:                   90 Calendar Days (3-19-18 to 6-17-18)

Construction Status:  As of March 31, 2018, the contractor has mobilized, acquired materials, and is scheduled to begin work.