Page 249 - Budget FY 2022-2023 - Update
P. 249

Adopted Budget 2023                                                          City of McAllen, Texas


                                           AIRPORT CAPITAL IMPROVEMENT
                                                  Fund Balance Summary

                                                                Actual     Adj. Budget   Estimated      Budget
                                                                20-21        21-22         21-22        22-23

            RESOURCES

            BEGINNING FUND BALANCE                           $  (1,068,496)   $  (467,837)   $  (1,509,710)   $  487

            Revenues:
              Grant Reimbursement - FAA                      $   6,734,309     $  41,928,260     $  5,929,075     $  40,301,436

            Total Revenues                                       6,734,309      41,928,260      5,929,075      40,301,436

            Other Financial Sources:
                Transfer In - Passenger Facility Charge Fund      655,380      3,090,563      751,679      2,909,805
                Transfer In - McAllen International Airport Fund     89,723      8,285,397      1,044,773      8,211,787

            Total Revenues and Other Sources                     7,479,412      53,304,220      7,725,527      51,423,028

            TOTAL RESOURCES                                  $   6,410,918     $  52,836,383     $  6,215,817     $  51,423,515

            APPROPRIATIONS

            Capital Projects *
              Cargo Ramp Design / Construction               $         -    $  8,813,000    $     -    $  8,813,000
              Cooling Towers                                       25,462            -            -             -
              Floor Scrubber                                           -        70,000        50,841            -
              GA Land Acquisition                                      -      2,874,097       11,380      2,862,717
              GA Master Business Plan                                  -        50,000            -         50,000
              RIM-HS1 Environmental and Design                         -             -            -        130,000
              Pavement Management Program                              -             -            -        240,000
              Master Plan Update                                    2,051            -            -             -
              Mobile GPU / PC Air Unit                                 -        250,000      176,273            -
              Monument and Wayfinding Signs                        38,193            -            -             -
              Parrallel Runway Feasibility Study                       -        500,000           -        500,000
              Runway & Taxiway Safety Improvements               7,854,923      29,663,623      6,583,964      27,486,041
              Runway 14-32 Rehabilitation                              -      3,101,000           -       3,101,000
              Terminal Amenity                                         -        500,000           -        500,000
              Terminal Elevator Rehabilition                           -        660,000       25,000       635,000
              Terminal Expansion Feasibility Study                     -        500,000           -        500,000
              Terminal HVAC & Lighting Efficiency Improvements         -      2,200,000           -       2,200,000
              Terminal Passenger Boarding Bridge Improvements          -      2,122,500           -       2,122,500
              Terminal Tiled Roof Replacement                          -      2,000,000       79,400      2,282,770
            Total Project Cost                               $   7,920,629    $  53,304,220    $  6,926,858    $  51,423,028

            Other Financing Sources (Uses):
              Transfer Out - Airport Fund                              -             -         6,500            -

            TOTAL APPROPRIATIONS                             $   7,920,629     $  53,304,220     $  6,933,358     $  51,423,028

            Revenues over/(under) Expenditures                    (441,217)          -       792,169            -

            Other items affecting Working Capital                      -        562,894      718,028            -

            ENDING FUND BALANCE                              $  (1,509,710)   $  95,057    $    487    $      487