Page 258 - Budget FY 2022-2023 - Update
P. 258
City of McAllen, Texas Adopted Budget 2023
SIGNIFICANT NONROUTINE CAPITAL PROJECTS REQUESTS
PROJECT NAME: FIREFIGHTER TRAINING FACILITY CENTER
Estimated Total Cost of Project (All Accounts)
$3,544,180
Funding Source
Infrastructure and Improvement Fund
Location
10700 North La Lomita Road
Work to be Performed
New Construction of Firefighters Training Facility
Center�
Reason for Work
To provide state of the art classroom and training
facility for internal, local, state, regional, national, and
international first responders.
Impact on Operating Budget
Moderate
Personnel Supplies Services Capital Other Total
$ - $ - $ 80,000 $ - $ - $ 80,000
PROJECT NAME: FIRE STATION #8
Estimated Total Cost of Project (All Accounts)
$3,209,180
Funding Source
Infrastructure and Improvement Fund
Location
Tres Lagos
Work to be Performed
New construction of Fire Station #8�
Reason for Work
To maintain the standards of emergency response
times for residents and businesses in that area�
Impact on Operating Budget
Moderate
Personnel Supplies Services Capital Other Total
$ - $ - $ 80,000 $ - $ - $ 80,000
- 256 - Table of Contents