Adopted Budget 2023                                                          City of McAllen, Texas



                                               Strategic Business Plan

                                Goal 6: Enhance McAllen’s infrastructure network. (continued)

                                                                 Total
                                       Department /                      Estimated   Budget
              No.        Objective                  Time- line  Project                         Status - Rationale
                                         Agency                          FY 21-22  FY 22-23
                                                                 Cost
                                                                                            Byron Nelson, west of 2nd
                                                                                            Street-Proposed storm
                                                                                            sewer infrastructure
                                                                                            improvements to address
                                                   October 2021                             an area with a limited
                   2nd Street at Byron
             6�3�29                     Engineering  - September   $431,744  $153,207  $278,537  and undersized existing
                   Nelson
                                                      2022                                  storm sewer system that is
                                                                                            prone to localized shallow
                                                                                            flooding, especially during
                                                                                            moderate to severe storm
                                                                                            events�
                                                                                            Quince at N 8th-Proposed
                                                                                            storm sewer infrastructure
                                                                                            improvements to address
                                                   October 2021                             an area with a limited
             6�3�30  Quince Avenue at N� 8th   Engineering  - September   $369,300  $95,550  $273,750  and undersized existing
                                                                                            storm sewer system that is
                   Street
                                                      2023                                  prone to localized shallow
                                                                                            flooding, especially during
                                                                                            moderate to severe storm
                                                                                            events�
                                                                                            Collardo Subdivision:
                                                                                            Savannah Avenue at S� 26th
                                                                                            Street-Upgrade existing
                                                   October 2022                             storm sewer system serving
                   Collardo Subdivision
             6�3�31                     Engineering  - September   $262,000  $0    $262,000  the Collardo Subdivision
                   Drainage Improvements
                                                      2023                                  and provide additional
                                                                                            offsite stormwater storage
                                                                                            capacity within an existing
                                                                                            City owned drainage ditch�
                                                                                            McAllen Foreign Trade
                                                                                            Zone Stormwater Detention
                                                   October 2021                             Pond-Upgrade of existing
                   Trade Zone Pump Station
             6�3�32                     Engineering  - September   $250,000  $12,321  $237,679  stormwater pump station to
                   Improvement
                                                      2023                                  include pump replacement
                                                                                            with new backup power
                                                                                            supply�
                                                                                            Beaumont Avenue between
                                                                                            South 1st and South 2nd
                   South 1st Street at             October 2022                             Streets-Introduce new
             6�3�33  Beaumont Avenue    Engineering  - September   $163,500  $0    $163,500  storm sewer infrastructure
                   Drainage Improvements              2023                                  to address flooding during
                                                                                            moderate to heavy storm
                                                                                            events�
                                                                                            Mona Avenue between
                                                                                            North 23rd Street and
                                                                                            the NW Blueline Drainage
                                                   October 2022                             Ditch-Upgrades to aged
             6�3�34  Mona Avenue Drainage   Engineering  - September   $130,000  $0  $130,000  storm sewer infrastructure
                                                                                            required to address flooding
                   Improvements
                                                      2023                                  at the intersection of Mona
                                                                                            Avenue at North 23rd Street
                                                                                            improvements to the overall
                                                                                            system�
                                                                                            Primrose at Bicentennial-
                                                                                            Proposed storm
                                                                                            sewer infrastructure
                                                                                            improvements to address
                                                   October 2021                             an area with a limited
                   Primrose Avenue at
             6�3�35                     Engineering  - September   $203,224  $81,289  $121,935  and undersized existing
                   Bicentennial
                                                      2023                                  storm sewer system that is
                                                                                            prone to localized shallow
                                                                                            flooding, especially during
                                                                                            moderate to severe storm
                                                                                            events�