Goal 6: Enhance McAllen’s infrastructure network. (continued)
Department / Total Project Estimated Budget
No. Objective Time- line Status - Rationale
Agency Cost FY 23-24 FY 24-25
Country Club Terrace-
Storm sewer infrastructure
improvements to address
Country Club an area with a limited and
6�3�24 Terrace Drainage Engineering October $391,825 $1,065 $225,000 undersized existing storm
Improvements sewer system that is prone
to localized shallow flooding,
especially during moderate to
severe storm events�
Lindberg Avenue (South Col�
Rowe to South 6th Street)-
Lindberg Avenue Project is for Storm Sewer
6�3�25 Drainage Engineering October $347,700 $22,700 $300,000 System that is prone to
Improvements localized shallow flooding,
especially during moderate to
severe storm events�
Burns Drive between
Sandy Lane to Kent Lane-
Burns Drive Drainage Introduce new storm sewer
6�3�26 Engineering October $331,750 $21,500 $289,250 infrastructure to address
Improvements flooding along Burns Drive
between Sandy and Kent
Lanes� 2018 Bond Project�
Dallas Avenue at South
1st Street-Storm sewer
infrastructure improvements
Dallas Avenue at South to address an area with
6�3�27 1st Street Drainage Engineering October $280,520 $20,000 $240,000 a limited and undersized
Improvements existing storm sewer system
that is prone to localized
shallow flooding, especially
during moderate to severe
storm events�
North 4th Street at Tulip
Avenue (rear alley)-Upgrade
North 4th Street at to existing storm sewer
6�3�28 Tulip Avenue Drainage Engineering October $276,279 $12,550 $256,450 infrastructure to address
Improvements flooding in alley and rear of
properties during moderate
to heavy storm events� 2018
Bond Project�
Gray Subdivision: North 46th
Street at Pecan Boulevard-
Gray Subdivision Upgrade/improve existing
6�3�29 Drainage Outfall Engineering October $266,950 $15,750 $243,200 storm sewer outfall serving
Improvements the Gray Subdivision to
address flooding during
moderate to heavy storm
events� 2018 Bond Project�
Beaumont Avenue between
South 1st Street and South
2nd Street-Storm sewer
South 1st Street infrastructure improvements
to address an area with
6�3�30 at Beaumont Engineering October $240,623 $11,470 $222,500 a limited and undersized
Avenue Drainage
Improvements existing storm sewer system
that is prone to localized
shallow flooding, especially
during moderate to severe
storm events�
Houston Avenue at South
2nd Street-Upgrade existing
Houston Avenue storm sewer infrastructure
6�3�31 at South 2nd Engineering October $235,000 $10,000 $217,000 (siphon under irrigation
canal) to improve function
Street Drainage
Improvements and efficiency of upstream
storm sewer network� 2018
Bond Project�