McAllen Public Works Automotive Warehouse Expansion & Elevator

The existing public works facilities for the anticipated elevator implementation and regular vehicles maintenance garage expansion. The project requirements are to provide an expansion and new addition to existing warehouse building consisting of selective demolition (of existing), foundation, pre-engineered metal structure, insulated metal panels, metal roofing, insulating liner system, openings, finishes, and specialties. Also included, new site work, mechanical, plumbing, electrical, communications, and fire suppression with alarm system and wall accessories, as well as other components and material required for a complete installation.

Architectural Firm: Negrete & Kolar Architects
Construction Company: Rigney Construction
Original Contract: $986,000.00
Change Order: $0
Original Contract (Days): 120 – Working Days 
Contract End Date October 24, 2019- March 31, 2020

The 24, 2019 Notice to Proceed was issued on October 10, 2019. The project is 15 working days into construction. Crews have started to remove the asphalt surface and have removed the canopy located on the west side of this facility.