N 6th Street at Date Palm Avenue Drainage Improvements

This project consists of upgrades to an existing storm sewer system at the intersection of N. 6th Street and Date Palm Avenue. The improvements include replacing existing storm sewer inlets and related piping. The project is funded by the Community Development Block Grant program under the FY16-17 cycle.

Construction Company:          Gonzalez Enterprises, LLC.
Original Contract:                     $ 37,985.80
Contract Days:                          15 (working)

Construction Status: As of December 31, 2017, the contractor has completed the removal of the existing storm sewer elements and all related demolition. Crews have also completed installation of the proposed inlets and laterals at the north end of the intersection. Preparation is underway for construction at the south end of the intersection. The project is on schedule for completion in mid-January.

Demolition and preparation operations

  • 51

Inlet and curb and gutter construction at north end of intersection

  • 52