Kennedy Avenue Drainage Improvements
This project consists of the installation of approximately 3,630-linear feet of storm drain pipe along Kennedy Avenue, Jackson Avenue, and Colonel Rowe Boulevard. The proposed system will tie into the existing storm sewer system on Houston Avenue. Storm drain inlets will also be installed to efficiently intercept surface runoff.
|
|
Construction Company: |
RDH Site and Concrete, LLC |
Original Contract: |
$669,506.00 |
Change Order: |
$0 |
Original Contract (Days): |
150 – Working Days |
Contract End Date |
Sep. 20, 2019 –Feb. 20, 2020 |
Change Order (Day’s): |
0 |
Construction Status: During the month of October, construction shop drawings and submittals were approved. The contractor has reported a material delay for pre-cast structures from manufacturer. Finalization of Traffic Control Plan in progress. Construction anticipated to begin November.